We are building a house. Not just any house, but an 1850s-style octagon house, the kind that used to be found here and there on the Midwestern prairie. For most of the construction we use existing materials that Jim has scrounged over the years. Read on and enjoy! — Jim & Sam




Aug 3
The heat here has been enervating. We’ve had only two days of normal temperatures in the last six weeks. Every other day in the period has been in the upper 80’s and nineties. But, by far the humidity has been the worse problem. We sweat just standing still. The afternoons are often unbearable. As a result the progress is slow. We have the sheeting up on four of the eight walls. A rudimentary staircase is in to the basement and the second floor, and I have begun to frame out the interior walls on the first floor. Today the electrician stopped by to begin wiring the exterior walls and to set the electrical panel. The cupola is framed and six of the eight sides are roofed. We have also begun the stone facing in order to prepare for the setting of the electric meter. This has been one of the hottest summers on record here and has delayed progress by at least three weeks. We are hoping for a long cool fall in order to catch up. Jim
A real pattern has set in. In the morning I grunt, Jim groans, and we decide to start the day working on the house. Depending on the humidity we are able to work until ten o’clock and have a tea break. A few complaints from Jim about the weather and arthritis, and I smile, nod, and wipe the sweat from my brow. After we are recuperated, we head back to the worksite to either continue on the task we had left off on, or as the sun turns full bore from behind the maple and hackberry that shade our site shift to a shadier spot and start a new task. A groan from Jim to show he still moves. I grunt to acknowledge and move in the pattern of our day. Sam


July 12
The heat and humidity has really slowed things down here. It was a whole week in the 90’s and outside work was only possible for a few hours in the mornings. We did get a two day break and managed to get the cupola framework up and in place. The roof will have to wait as the heat has returned. The final shape of the house is now visible and it is quite a show stopper. We have also begun to get the sub-floor in over the kitchen and some of the second floor. Jim



Dave and John came this morning unexpectedly to help set the timbers on the second floor (Good thing that I spent yesterday evening cutting and measuring them so they were ready!) Sam decided he wanted to go with the 1866 barn framing timbers for the main supports rather than the laminated beams we made up for the rest of the structural members out of 2x10’s . It makes for a little more work but the look should be worth it…especially the one that has the date on it in big black numbers. Sam had to square up a damaged side of one using the adze…an experience only few have had in the last century! We started at six and were done by ten. Now for the attic joists!
Jim
Dennis stopped over yesterday morning and today to help us set the attic floor joists. He was an immense help. The days are really heating up and we must take breaks during the heat of the day. A few days of futzing and we will be ready to think about roof rafters. A little bit every day gets the job done.